SAP PM explained: functional locations and equipment, task lists and maintenance plans, the work order cycle and statuses, and the master data that makes it work

SAP PM, SAP Plant Maintenance, from the maintenance side: the master data objects from functional locations and equipment to task lists, maintenance plans, measuring points and catalogs, the work order cycle from notification to settlement with its system statuses and classic transaction codes, notification types and codes, plans and scheduling, and the master data problems that spoil the history. With a drawing of the master data and work cycle.

Master DataWork ManagementApplications
Line drawing of SAP PM master data from functional locations to maintenance plans, and the work order cycle from notification to settlement with statuses

Key takeaways

  • SAP PM, plant maintenance, is the maintenance module of SAP ERP and of asset management in S/4HANA. It holds the asset structure, the job plans and schedules, and the work order history.
  • The master data is a hierarchy of functional locations with equipment installed in them, plus bills of materials, task lists, maintenance plans, measuring points and catalogs.
  • Work runs from a notification to an order that is planned, released, done, confirmed, technically completed and settled. Each step has a status that reports can rely on.
  • Most SAP PM problems are master data problems: a flat hierarchy, equipment never created, catalogs nobody uses, task lists without durations or parts.
  • The system works when the process around it does. A notification with good codes, an order with a real plan and a confirmation with what was found are what make the history worth having.

A site runs SAP PM for ten years and has a quarter of a million closed orders. Someone asks which pumps fail most and why. The answer is not in the system, because most orders were raised against the area rather than the pump, the damage and cause codes were left blank or set to 'other', and the pumps themselves were never created as equipment. The system did everything it was asked to. It was never asked for the right things.

This guide covers SAP PM, also called SAP Plant Maintenance, from the maintenance side: the master data objects and how they fit together, the work order cycle and its statuses, notification types, and the master data problems that spoil the history. It is written for planners, engineers and supervisors rather than SAP configurers. Enco is not affiliated with SAP, and the transaction codes named are the classic ones, with S/4HANA offering Fiori apps for the same steps.

Master data and the work cycle

SAP PM has two halves. The master data describes the plant and the standard work: where everything is, what it is made of, what maintenance it needs and when. The transactional data is the work itself: notifications, orders, confirmations and their costs. The master data is set up once and maintained, and the transactional data is created every day from it.

Each half depends on the other. A maintenance plan calls a task list for a piece of equipment and generates an order. A notification raised against equipment carries its catalog codes into the history. If the master data is thin, every order is planned from scratch, and the history cannot be read by asset, failure mode or cost.

SAP PM · MASTER DATA AND THE WORK CYCLEMASTER DATAFUNCTIONAL LOCATIONS · IL01PLANT-210CRUSHINGCV-210 CONVEYORCV-210-DR DRIVEEQUIPMENT · IE01MOTOR 10001234INSTALLED AT CV-210-DRBOM · IB01BEARINGS, SEALS, FANTASK LIST · IA0510 ISOLATE AND TEST20 INSPECT DRIVE, 2 HMAINT. PLAN · IP41EVERY 13 WEEKSMEASURING POINT · IK01RUN HOURS COUNTERBEARING TEMPERATURECATALOGS · QS41PART, DAMAGE, CAUSERAISED AGAINSTPLAN CALLS PREVENTIVE ORDERSCODES COMPLETEDNOTIFICATIONIW21OSNOORDERIW31CRTDRELEASEIW32RELSCHEDULE, DOWEEKLY PLANRELCONFIRMIW41PCNF, CNFTECOIW32TECOSETTLE, CLOSEKO88CLSDWORK CYCLE · SYSTEM STATUSES DRIVE BACKLOG, COMPLIANCE AND COST REPORTSSAP-0101 · MASTER DATA AND WORK ORDER CYCLE · REV A
Fig. 1 · The SAP PM master data, from functional location and equipment to task list and maintenance plan, and the work order cycle from notification to settlement with its statuses

SAP PM records what it is given. The quality of the history is set by the master data and the codes.

The master data objects

The functional location hierarchy is the backbone. It is usually built to a structure such as ISO 14224, from site and area down through system and unit to the maintainable item positions, with tags that match the drawings. Equipment is installed at those positions, so a gearbox that moves to the workshop and back keeps its own history.

ObjectClassic transactionWhat it isWhy it matters
Functional locationIL01A place in the plant hierarchy where equipment is installed, such as a conveyor drive positionThe structure the work and cost history hang from
EquipmentIE01An individual, serialised item that can be installed at a functional location and movedKeeps its own history wherever it is installed
Bill of materialsIB01The spare parts that make up a piece of equipment, linked to material numbersLets planners pick parts onto an order
Task listIA05, IA01, IA11The operations, trades, durations and parts for a job, general or for one equipment or locationThe standard job plan, reused by orders and plans
Maintenance planIP41, IP42When a task list is called, by time, counter or a strategy of packagesGenerates preventive orders on schedule
Measuring point and counterIK01A reading taken on an object, such as run hours or a thicknessDrives counter-based plans and condition records
CatalogsQS41Damage, cause, object part and activity codes used on notificationsWhat makes failure history countable

The work order cycle

Work in SAP PM follows the same work order cycle as any CMMS, with a system status at each step. The statuses are what reports, backlogs and KPIs rely on, so an order left released after the work is done counts as backlog, and an order closed without confirmations shows no labour. Most sites add user statuses, such as awaiting approval, awaiting parts or ready to schedule, to show where work is held between creation and release.

StepClassic transactionWhat happensStatus
NotificationIW21A malfunction or request is raised against a functional location or equipmentNotification outstanding (OSNO)
Order createdIW31, or from the notificationThe planner creates an order, adds operations, trades, durations and componentsCreated (CRTD)
ReleasedIW32The order is approved and released, reservations and purchase requisitions go outReleased (REL)
Scheduled and doneCapacity planning, or a separate scheduling toolThe order is put in the weekly schedule and the work is doneReleased (REL)
ConfirmedIW41Hours, actual work and completion are confirmed against each operationPartly confirmed (PCNF), Confirmed (CNF)
Technically completeIW32The notification is completed with its codes and the order closed for workTechnically completed (TECO), notification completed (NOCO)
Settled and closedKO88, IW32Costs settle to the cost centre or project and the order is closedClosed (CLSD)

Notifications and codes

The notification is where the failure history starts. A malfunction report carries the object part, damage and cause codes from the catalogs, and those codes are the only way to count failures by mode across hundreds of assets. A catalog that is too long, too vague or optional produces codes nobody trusts. A short catalog built from the site's equipment classes and failure modes, with the codes completed when the order is technically complete by someone who saw the job, produces history that root cause analysis and reliability engineering can use.

TypeNameUsed for
M1Maintenance requestWork wanted that is not a failure, such as an improvement or a minor job
M2Malfunction reportSomething has failed or is failing, with damage and cause codes
M3Activity reportA record of work already done, such as an inspection result

Plans, task lists and scheduling

Preventive work comes from maintenance plans. A single cycle plan calls a task list every so many weeks or run hours. A strategy plan calls packages of tasks at different intervals from one plan. The plan generates orders ahead of their due date by a call horizon, which gives the planner time to prepare them. The task list carries the operations, trades, durations and parts, so the generated order arrives already planned, which is the point of the preventive maintenance program.

Scheduling is where many sites go outside the core module. The weekly schedule, with its capacity by trade and frozen list, is often built in a separate scheduling tool or spreadsheet fed from SAP, and the results go back as dates on the orders. However it is done, the planning and scheduling process and its measures, such as backlog in crew-weeks, need the order durations and statuses to be right.

Where SAP PM goes wrong

Most SAP PM complaints are not about the software. They come from master data that was loaded once at go-live and never maintained, and from a process where the system is filled in after the work rather than used to run it. Master data is a maintained asset, with an owner, a standard and a change process, and an asset hierarchy rebuild is often the single change that makes the history usable.

ProblemWhat it costs
Flat or inconsistent functional locationsCost and history cannot be rolled up by area, system or equipment class
Equipment never created, work raised on locations onlyNo history follows a motor or gearbox when it is changed out
Catalogs too long, too vague, or optionalDamage and cause codes are skipped or always 'other', so failures cannot be counted
Task lists without durations, trades or partsOrders cannot be scheduled or kitted, and planners rebuild each one
Maintenance plans with stale intervalsPreventive work that no longer matches the strategy, or plans calling work for removed equipment
Orders left open after the workBacklog that is not real, and costs that never settle

Common mistakes

  • Raising work against an area or system instead of the equipment or position.
  • Catalog codes optional, or completed by someone who did not see the job.
  • Task lists with no durations, so the backlog cannot be counted in hours.
  • Orders technically completed weeks after the work, or never.
  • Maintenance plans left calling work for equipment that was removed.
  • User statuses added for every possible state, so nobody keeps them current.
  • Treating master data as a go-live task rather than an ongoing one.

Common questions

What is SAP PM?

SAP PM, or SAP Plant Maintenance, is the part of SAP's ERP software that manages maintenance. It holds the technical structure of the plant as functional locations and equipment, the job plans as task lists, preventive schedules as maintenance plans, and the work itself as notifications and maintenance orders, with costs flowing to finance. In S/4HANA it sits under asset management, with Fiori apps beside the classic transactions.

What is the difference between a functional location and equipment in SAP?

A functional location is a place in the plant where a function is performed, such as the drive position on a conveyor. Equipment is an individual physical item, such as a particular motor with a serial number, that is installed at a functional location. When the motor is changed out, the new one is installed at the same location and the old one keeps its own history, so the history of the position and of each item are both kept.

What is the difference between a notification and an order in SAP PM?

A notification records that something needs attention: a malfunction, a request or a record of work done, with codes for the object part, damage and cause. A maintenance order is the plan and record of the work: its operations, trades, hours, parts, costs and confirmations. One notification usually leads to one order, and the notification's codes are completed when the order is technically complete.

What are the order statuses in SAP PM?

The main system statuses are created (CRTD), released (REL), partly confirmed (PCNF), confirmed (CNF), technically completed (TECO) and closed (CLSD). Notifications move through outstanding (OSNO), in process (NOPR) and completed (NOCO). Sites usually add user statuses on top, such as awaiting parts or ready to schedule, to show where work is held up.

What are the main SAP PM transaction codes?

Commonly used classic transactions include IW21 to create a notification, IW31 to create an order and IW32 to change it, IW41 to confirm time, IL01 to create a functional location, IE01 to create equipment, IA05 for a general task list, IP41 and IP42 for maintenance plans, IK01 for a measuring point, and IW38 or IW39 to list orders. S/4HANA also offers Fiori apps for the same steps.

Key terms

Plain-language definitions from our glossary for the concepts this article leans on.

Standards and further reading

Related case studies and tools

Related reading

Working through something like this?

See how we approach these initiatives, or tell us what you are dealing with.