Engineering drawings: the types of drawing, the parts of a drawing sheet, reading a general arrangement, AS 1100 and keeping drawings controlled
Engineering drawings as plant teams use them: general arrangements, assemblies, detail and fabrication drawings, layouts and isometrics, the title block, revision block, projection symbol, views, dimensions, notes and parts list, reading a general arrangement in order, first and third angle projection under AS 1100 and ISO 128, and the numbering, revisions and register that keep drawings current. With an illustrative GA sheet.

Key takeaways
- An engineering drawing is the controlled record of what something is: its shape, size, material and how it goes together. The drawing number and revision are what make it a record.
- Most plant work uses a handful of drawing types: general arrangements, assemblies, detail drawings, fabrication drawings, layouts and piping isometrics, beside the process and electrical diagrams.
- Read a general arrangement in order: title block and revision, projection symbol, views, overall size and interfaces, notes, then the parts list.
- Australian drawings to AS 1100 are normally in third angle projection, while many European drawings are first angle. The symbol in the title block says which.
- A drawing is only useful if it is current. A register, revisions recorded on every issue, native files kept and redlines turned into as-builts are what keep it so.
A fitter is sent to replace a worn pump baseplate with one fabricated from the drawing in the workshop file. The new baseplate arrives with its hold-down holes 40 mm out. The drawing was revision B. The site register shows revision D, issued after the pump was changed to a different frame size, and nobody withdrew the old print.
This guide covers engineering drawings as plant teams use them: the kinds of drawing, the parts of a drawing sheet, how to read a general arrangement, projection and the standards behind it, and keeping drawings controlled. It sits beside the guides to P&ID symbols, single line diagrams and as-built drawings. The drawing shown is illustrative.
Kinds of engineering drawing
Drawings divide into those that define shape, such as general arrangements, assemblies and details, and those that define how a system works, such as P&IDs, single line diagrams and loop diagrams. Most physical items have a general arrangement at the top, assembly drawings beneath it, and a detail drawing for each made part.
| Type | What it shows | Used for |
|---|---|---|
| General arrangement (GA) | The whole item assembled, its main dimensions, interfaces and the parts that make it up | Approval, installation, layout checks, and finding the detail drawings |
| Assembly and sub-assembly | How parts go together, with balloons to a parts list | Building and maintaining the item |
| Detail (part) drawing | One part, fully dimensioned and toleranced, with material and finish | Making or reverse engineering the part |
| Fabrication drawing | Welded or bolted steelwork with weld symbols, cut lengths and hole positions | The fabricator's shop |
| Layout and plot plan | Where equipment sits on a site or in a building, on grid lines | Planning space, access and maintenance clearances |
| Piping isometric | One pipeline drawn in three dimensions with its fittings and lengths | Fabricating and installing pipe |
| Process and electrical | P&IDs, single line diagrams, loop diagrams, schematics | How the plant works and is wired, rather than its shape |
The parts of a drawing sheet
Every sheet carries the same furniture around the views. The title block identifies the drawing, the revision block records its history, and the projection symbol says how the views relate. In Australia, AS 1100 sets the conventions for sheets, lines, lettering, projection and dimensioning, and ISO 128 and ISO 7200 do the same internationally.
| Part | What it is | What to check |
|---|---|---|
| Title block | Drawing number, title, scale, sheet size, revision, and who drew, checked and approved it | That the number and revision match the register |
| Revision block | Each revision with its letter or number, date, description and approval | What changed since the copy you know |
| Projection symbol | Whether the views are in first or third angle projection | Australian drawings to AS 1100 normally use third angle, European ones often first angle |
| Views | Orthographic views such as front, plan and side, with sections and enlarged details | Which view is which, and where each section is cut |
| Dimensions and tolerances | Sizes, positions and the allowed variation, from datums | Which dimensions are critical, and the general tolerance note |
| Notes | General notes on material, finish, welding, bolting and standards | Requirements that apply to the whole drawing |
| Parts list | Item numbers, descriptions, quantities and part or drawing numbers | Balloons on the views match the list |
| Zone grid | Letters and numbers around the border that locate features | Used to point to a spot in a revision note or a query |
Check the revision before anything else. A correct reading of the wrong revision is still wrong.
Reading a general arrangement
A general arrangement is read from the outside in. Confirm you have the right drawing at the right revision, work out how the views relate, then read the overall size and the interfaces before the detail. Interfaces are where most site problems are found: hold-down bolts, pipe connections, cable entries and the clearances needed to maintain the item.
| Step | Look at | Why |
|---|---|---|
| Title block and revision | Is this the current revision of the drawing you need | Working from a superseded copy is the most common drawing error |
| Projection symbol | First or third angle | It decides where each view sits relative to the others |
| Views and orientation | Which view is the front, which is the plan, where north or the flow direction is | Everything else is read against this |
| Overall size and interfaces | Envelope dimensions, centrelines, datums, connection points and hold-down positions | What the item must fit and connect to |
| Notes | Material, finish, weld and bolting requirements, referenced standards | Requirements that are not drawn |
| Parts list and references | Balloons, item numbers and the detail drawings each refers to | Where to go for the full detail of a part |
| Revision clouds | Clouds or triangles marking what changed in this revision | The quickest way to see what is new |
Projection and views
Orthographic projection shows an object in flat views from set directions. In third angle projection, used for Australian drawings to AS 1100, each view is placed on the side it is seen from: the plan above the front view, the right side view to its right. In first angle projection, common in Europe, the views are placed on the opposite side. Sections show the inside of a part along a cutting line, and details enlarge a small area. Isometric views, which show the object in three dimensions, are often added to help reading but are not used for dimensions.
Keeping drawings controlled
Drawings stay useful only while they match the plant. That needs a numbering scheme, a revision recorded on every issue, a register that says which revision is current, native CAD files kept with the PDFs, and every field change marked up and drawn as built. Document control covers the register, and management of change is what triggers the update. When drawings are missing or unreliable, a measured survey or a laser scan can rebuild them.
| Practice | What it means | Notes |
|---|---|---|
| Numbering | One drawing number per drawing, never reused, with sheets numbered within it | A number that tells you the site, area or discipline helps |
| Revisions | A revision letter or number for each issue, recorded in the revision block and the register | Many sites use letters before construction issue and numbers after it |
| The register | A list of every drawing, its current revision and status | The source of truth for what is current. See document control |
| Native files | The CAD model or file the PDF came from, kept with it | Without it, the next change starts with redrawing |
| As-built | Drawings updated to match what was built, from marked up redlines | See as-built drawings and redlines |
| Superseded copies | Old revisions withdrawn from use and marked superseded | Printed copies in the field are the usual leak |
Common mistakes
- Working from a printed copy without checking it against the register.
- Misreading first angle drawings as third angle, which mirrors the part.
- Scaling dimensions off a PDF instead of using the dimensions given.
- Changes made in the field and never marked up on the drawing.
- PDFs kept without the native CAD files they came from.
- Reusing a drawing number for a different item.
- Missing interface and maintenance clearance information on general arrangements.
Common questions
What is an engineering drawing?
An engineering drawing is a technical drawing that defines a part, assembly, structure or system precisely enough to make, install, inspect or maintain it. It shows the shape in standard views, gives dimensions and tolerances, names materials and finishes, and carries a title block with a drawing number and revision so it can be controlled. In Australia the conventions are set out in the AS 1100 series, and internationally in ISO 128 and related standards.
What is a general arrangement drawing?
A general arrangement (GA) drawing shows a complete item assembled, such as a pump skid, a conveyor head end or a structure, with its overall dimensions, interfaces, main components and a parts list. It is used to approve a design, plan installation and check fit, and it refers to the assembly and detail drawings that define each part.
What is the difference between first angle and third angle projection?
Both arrange orthographic views around a front view, but in opposite positions. In third angle projection the plan view sits above the front view and the right side view to the right of it. In first angle projection the plan sits below and the right side view to the left. Australian drawings to AS 1100 normally use third angle, while many European drawings use first angle. The projection symbol in the title block says which, and misreading it mirrors the part.
What is AS 1100?
AS 1100 is the Australian series of standards for technical drawing. Part 101 covers general principles such as sheet sizes, lines, lettering and projection, Part 201 covers mechanical engineering drawing, and other parts cover structural, architectural and other disciplines. It aligns broadly with the ISO 128 series used internationally.
What should be in a drawing title block?
At least the drawing number, title, revision, scale, sheet size and sheet number, the projection symbol, and who drew, checked and approved the drawing with dates, plus the organisation's name. ISO 7200 lists the data fields used in title blocks. A revision block nearby records each revision and what changed.
Key terms
Plain-language definitions from our glossary for the concepts this article leans on.
Standards and further reading
- AS 1100.101-1992 Technical drawing, general principles (Standards Australia)
- AS 1100.201-1992 Technical drawing, mechanical engineering drawing (Standards Australia)
- ISO 128-1:2020 Technical product documentation, general principles of representation, introduction and fundamental requirements (ISO)
- ISO 7200:2004 Technical product documentation, data fields in title blocks and document headers (ISO)