Permit to work and isolation: the stages of a permit, isolating and proving dead, and the link to the work order

How permit to work systems are usually structured: the stages of a permit and who signs at each, the permit types a site holds, the steps of isolation and proving dead, how the permit and the work order fit together so the permit lead time is in the schedule, and handover, suspension and close. A description of common practice, not a substitute for a site procedure.

Work ManagementPlanning & Scheduling
The stages of a permit to work from request to close, with who signs at each and isolate and prove marked

Key takeaways

  • A permit to work is a written system for controlling hazardous work: it says what work is allowed, where, by whom, for how long, and what has to be in place before it starts. It does not make work safe by itself. It records that the controls have been put in place and checked.
  • Every permit runs through the same stages: request, plan, isolate and prove, issue, work, suspend or hand back, and close. Each stage has a person who signs for it, and the signatures mean something only if the person has checked what they sign.
  • Isolation is the step the rest rely on. Every energy source is isolated, locked, tagged, dissipated and proved dead, with a lock for every person working.
  • The permit controls the hazards of the work. The work order controls the work. When the two are linked, the permit's lead time is in the schedule and every isolation traces to a job.
  • The site's own procedure and the work health and safety laws of its jurisdiction govern. This guide describes how permit systems are usually structured, not what any one site must do.

A maintenance crew arrives at 7 am to change a conveyor pulley. The job was scheduled a week ago, the parts are kitted and the crane is booked. The permit has not been raised, because the planner did not know the job needed a confined space entry certificate for the transfer chute, and the issuing authority is in a shutdown meeting until ten. The crew waits three hours. On another site the same job starts on time, because the work order carried the permit type and the isolation standard, and the permit was prepared the day before.

This guide sets out how permit to work systems are usually structured: the stages of a permit and who signs at each, the types of permit a site holds, the steps of isolation and proving dead, and how the permit and the work order fit together so the permit is part of the plan rather than a surprise on the day. It is a description of common practice, drawn from the UK HSE's guidance and the Australian model codes, and it is not a substitute for a site's own procedure or the laws of its jurisdiction.

The life of a permit

Every permit system, whatever its forms look like, runs through the same stages. The work is requested and described. It is planned and its hazards assessed, and the isolations and controls are set. The isolations are made and proved. The permit is issued at the job, with the controls checked in place and the work party signed on. The work is done inside the permit's scope and time. At a shift change or a pause the permit is suspended or handed over. And when the work is finished the work party signs off, the equipment is checked fit to return, the isolations are removed and the permit is closed.

Each stage has a person who signs for it. The names vary between sites, but the roles are usually an issuing authority who controls the area and issues the permit, an isolating authority who makes and removes isolations, and a performing authority who is in charge of the work party. A signature means the person has checked what they are signing for. A permit signed in an office for a job nobody has looked at is paperwork, not control.

  1. 1Request

    The work is described, with its location, equipment and the work order it belongs to

    Signs

    Performing authority

  2. 2Plan and assess

    The hazards of the job and the area are identified, the controls set and the isolations listed

    Signs

    Issuing authority

  3. 3Isolate and prove

    Every energy source is isolated, locked, tagged and proved dead or depressurised

    Signs

    Isolating authority

  4. 4Issue

    The permit is explained at the job, the controls checked in place and the work party signed on

    Signs

    Issuing and performing authorities

  5. 5Work

    The work is done within the permit's scope and time, with the permit displayed at the job

    Signs

    Work party

  6. 6Suspend or hand back

    At shift change or a pause the permit is suspended or handed over, with the state of the job written down

    Signs

    Both authorities

  7. 7Restore and close

    The work party signs off, the equipment is checked fit to return, isolations are removed and the permit is closed

    Signs

    Issuing authority

↓ One permit, one job, one work order. The closed permit goes to the work order history

Fig. 1 · The stages of a permit from request to close, with who signs at each. Isolate and prove is the stage every later stage relies on

Permit types

Most sites hold a general work permit and specific permits or certificates for the higher hazards. A specific permit adds its own controls on top of the general one, and a job can need more than one: changing a pulley inside a transfer chute might need a general permit, an electrical isolation, a confined space entry certificate and a hot work permit if the lagging has to be cut. The table lists the common types and what each typically adds. The site's procedure sets which it uses and what each requires.

PermitCoversTypically adds
General workWork on plant that is not covered by a specific permitThe base hazards, isolations and controls
Hot workWelding, cutting, grinding or any open flame or sparkFire watch, gas test where needed, removal of combustibles, a time limit
Confined space entryEntry into a space with restricted access and a risk from its atmosphere or contentsAtmosphere testing, a standby person, rescue arrangements, entry log
Electrical workWork on or near electrical equipmentElectrical isolation by an authorised person, test before touch, the site's electrical rules
Working at heightWork where a fall could cause injuryFall protection, exclusion zones, rescue plan
ExcavationDigging or penetrating ground or floorsServices located and marked, shoring, barriers
LiftingCritical or non-routine liftsA lift plan, competent crane crew, exclusion zone

Isolation and proving dead

Isolation is the step the rest of the permit relies on, and it follows the same sequence everywhere. Identify every energy source, which means reading the P&ID and the single line diagram, not relying on memory. Plan the isolation points and the order. Shut the equipment down by its normal controls. Operate each isolation point. Lock and tag each point, with a lock for every person working, directly or through a lock box. Dissipate stored energy. And prove the equipment is dead.

Two parts are most often skipped. Stored energy is easy to forget: a spring-applied brake, a hydraulic accumulator, a capacitor bank, a counterweight, a belt under tension. And proving dead is easy to assume. The electrical test is done with a tester that has itself been proved on a known live source before and after, and the mechanical proof is a try of the start and a read of the gauges. Standard isolations for repeat jobs save time and reduce error, as long as they are checked against the current drawings each time they are used.

StepWhat is doneWhat to watch
IdentifyEvery energy source: electrical, mechanical, hydraulic, pneumatic, stored, gravity, process and thermalThe P&ID and the single line, not memory
PlanThe isolation points and the order, written on an isolation list against the permitA standard isolation for repeat jobs, checked each time
Shut downStop the equipment by its normal controlsSo the isolation is not breaking load
IsolateOperate each isolation point to the isolated positionAn isolator, not a stop button or a control circuit
Lock and tagA personal lock and tag on each point for every person working, or a lock boxOne person, one lock, one key
DissipateRelease stored energy: discharge, vent, drain, block, lowerSprings, accumulators, capacitors and suspended loads
ProveTest that the equipment is dead: try the start, test for voltage, read the gaugeTest the tester before and after on a known live source

An isolation is only as good as the proof that it worked. Test the tester, then test the equipment, then test the tester again.

The permit and the work order

The permit and the work order are two records of the same job, and on many sites they live in separate systems that do not talk to each other. The work order is in the CMMS and controls the work: what is to be done, why, when, by whom and with what parts. The permit is in the permit system, often paper, and controls the hazards of doing it. When they are not linked, permits get raised for work nobody scheduled, isolations cannot be traced to a job, and jobs are scheduled with no allowance for the time the permit takes.

The link does not need to be elaborate. The work order carries the permit types the job needs and the isolation standard, so the planner can see the lead time when building the schedule and the job pack can include the isolation list. The permit carries the work order number. The closed permit is attached to the work order history. With that, the schedule for tomorrow tells the permit office which permits to prepare today.

Permit to workWork order
What it controlsThe hazards of doing the workThe work itself: what, why, when, who and with what
Lives inThe permit system, often paper or a separate applicationThe CMMS
Raised fromThe work order, at planning or on the dayA work request, a PM schedule or an inspection
Shared fieldsWork order number, equipment, location, description, scheduled datePermit number, isolation list reference
Closed whenThe work party signs off and the equipment is handed backThe work is done, the history recorded and the costs settled
Gap if they are not linkedPermits raised for work nobody scheduled, and isolations nobody can trace to a jobJobs scheduled with no permit lead time, and the crew waiting at the gate

Handover, suspension and close

Most permit failures in incident reports happen at a boundary: a shift change, a job paused overnight, two jobs on the same equipment, or the return to service. At a shift change the outgoing and incoming authorities meet at the job, the state of the work and the isolations are written on the permit, and the incoming authority signs to accept it. A suspended permit leaves the isolations in place and the equipment tagged as not fit to start. Two permits on the same equipment each hold their own locks on the shared isolations, so finishing one job cannot de-isolate the other.

Closing a permit is the step that returns the equipment to operations, and it is done in order. The work party signs off and removes their locks. The equipment is checked: guards back on, tools and people clear, the job left as the permit said. Only then are the isolations removed and the equipment handed back. If the work found something that needs a follow-up, the follow-up is a new work request, not an open permit left hanging.

Where permit systems go wrong

  • Permits signed in the office for jobs nobody has visited.
  • Isolations planned from memory or from drawings that are not current.
  • Stored energy left out of the isolation: springs, accumulators, capacitors, suspended loads.
  • Proving dead skipped, or done with a tester that was not itself proved.
  • One lock for the whole crew instead of one per person.
  • Shift handovers done at the crib room table rather than at the job.
  • Permits with no link to the work order, so the schedule has no permit lead time and the crew waits at the gate.
  • Too many permit types and forms, so people use the one they know rather than the one the job needs.

Common questions

What is a permit to work?

A formal written system used to control work that is hazardous or non-routine. The permit sets out the work, the equipment and location, the hazards, the precautions and isolations required, the people authorised to do the work and the time it is valid for. It is issued by an authorised person after the precautions are confirmed in place, accepted by the person in charge of the work, and closed when the work is finished and the plant is fit to return. The UK HSE's HSG250 is the most widely used guidance on how permit systems work.

What are the types of permit to work?

Most sites hold a general work permit and specific permits or certificates for higher hazards: hot work, confined space entry, electrical work, working at height, excavation and critical lifts. A specific permit adds controls to the general one, such as gas testing and a fire watch for hot work, or atmosphere testing and a standby person for confined space entry. Which permits a site uses, and what each requires, is set by its own procedure.

What is the difference between a permit to work and an isolation?

An isolation is the act of separating equipment from every source of energy and securing it so it cannot be re-energised, usually with locks and tags. A permit to work is the system that controls the job, of which the isolation is one part. A permit lists the isolations it relies on, and the work does not start until they are in place and proved. The isolation is removed only when the permit is closed or the work party has signed off.

What is lockout tagout?

The practice of placing a lock on an isolation point so it cannot be operated, and a tag that identifies who placed it and why. Each person working on the isolated equipment applies a personal lock, either directly or to a lock box holding the isolation keys, and removes it only when they have finished. In the United States it is required by OSHA 1910.147. In Australia the duty to manage the risk of hazardous energy sits in the work health and safety laws and codes of practice of each jurisdiction.

What does prove dead mean?

Confirming, after isolation, that the equipment is actually de-energised before anyone touches it. For electrical equipment it means testing for the absence of voltage with a tester that has itself been proved on a known live source before and after. For mechanical equipment it means trying the start, checking that pressure gauges read zero, and that moving parts are blocked or lowered. The isolation is only as good as the proof that it worked.

How does a permit to work link to a work order?

The work order describes the job and lives in the CMMS. The permit controls the hazards of doing it and lives in the permit system. They share the work order number, the equipment, the location and the scheduled date. When they are linked, the planner knows a permit is needed and builds its lead time into the schedule, the issuer can see what job each permit is for, and the closed permit becomes part of the work order history.

Key terms

Plain-language definitions from our glossary for the concepts this article leans on.

Standards and further reading

Related reading

Working through something like this?

See how we approach these initiatives, or tell us what you are dealing with.